Infrastructure Construction Works for a 20 MW Wind Farm in Panevėžys District

About the Project

Infrastructure construction works were completed for a 20 MW wind farm in Panevėžys district.

The project included site preparation, local road reconstruction, access road construction and installation of drainage systems required for long-term operation of the wind energy facility.

Scope of works:

  • 4.46 km of local road reconstruction
  • 38,975 m² of access roads constructed
  • 65,290 t of sand and 26,458 t of dolomite aggregate used for base layers
  • 81,555 m² of geotextile and geogrid installation
  • 2,002 m of drainage collectors installed
  • 1,136 m of drainage laterals installed
  • Dismantling of existing bridge
  • Installation of Multiplate culvert (7.34 m × 3.51 m)